Appserver update to Framework 3.8 (11, 18, 25 February)

Subject Appserver update to framework 3.8
Time frame 11 February, 7:00-7:30: Done
18 February, 7:00-7:30: Done
25 February, 7:00-7:30: Done
Planned or unplanned Planned
Expected impact Minor downtime for appserver, architect, composer and deployment, and updated behaviour to the appserver.
Features / changes The appserver will be updated to framework 3.8. To safely process the change, three separate updates are necessary. After the first update, application users will notice the change in UX that the 3.8 framework brings. The 2nd and 3rd update are required to allow new functionality to be added later but will not cause any difference in behaviour.
Who to contact Primary contact
Product(s) affected App Server,Architect,Composer,Deployment